KFC Hoarding Wall, GTA Mall Build-Out

The old boarded hoarding came down. A new full-height steel stud and drywall hoarding went up from scissor lifts, was taped and finished, and fitted with an access door, with the concourse handed back clean each session.

The Story

A hoarding wall is the first thing shoppers see of a build-out. It has to look finished.

A KFC unit inside a GTA mall was being built out behind construction hoarding. The existing hoarding was a plain boarded wall with a single door, the kind that reads as temporary from across the concourse. The landlord and the tenant's contractor needed it replaced with a proper full-height hoarding: framed straight, boarded and finished so it could carry paint or graphics, and fitted with a lockable access door.

Our crew removed the old hoarding and framed the new wall in light gauge steel stud to the mall's ceiling line, working from scissor lifts in the concourse. The wall was boarded, taped and finished to a paint-ready surface, and the access door was framed and hung. Work of this kind runs on the mall's schedule: framing and boarding while the concourse is closed, with tools, lifts and material cleared before the doors open.

The result is a hoarding that looks like part of the mall rather than a construction site, which is what a retail landlord expects from a drywall sub working in a live centre.

Project
KFC hoarding wall replacement
Sector
Retail, mall build-out
Location
GTA mall
Our role
Drywall and steel stud contractor
Scope
Removal of existing hoarding, light gauge steel stud framing from lifts, boarding, taping and finishing, access door
Photo record
Old hoarding, new framing and the finished wall
Scope of Work

What the hoarding scope covered.

  • Removal Existing boarded hoarding taken down and removed from the concourse.
  • Layout New wall line set to the lease line and the mall's ceiling and bulkhead conditions.
  • Steel stud framing Light gauge track and studs framed full height from scissor lifts, braced to the structure above.
  • Boarding Drywall installed to the concourse face, joints staggered, edges set for a clean line at the neighbouring storefront.
  • Taping and finishing Taped, sanded and finished to a paint-ready surface across the full wall.
  • Access door Framed opening and door installed so the tenant's contractor can lock the unit.
  • Mall logistics Lifts, tools and material cleared each session, concourse left clean for opening.
  • Handover Wall ready for the landlord's paint or graphics and the build-out behind it.
Photo Record

From the old hoarding to the finished wall.

Open any photo to view it full size, then use the arrows or swipe to move through the set.

Site Video

Two short clips from the concourse.

Framing the new hoarding wall from the lift.
Boarding the framed wall in the closed concourse.