Writing a drywall tender package that prices cleanly

Bids come back far apart when the tender lets each bidder fill the gaps differently. A package that closes the gaps gets numbers you can compare on the first pass.

Published 6 October 2026. 4 min read

Why bids come back that do not compare

Every bidder prices what the documents say and guesses at what they do not. Two estimators guessing differently produce two numbers, and the spread gets blamed on the subcontractors.

We cover the bidder side in what a drywall bid should include. This is the other direction. It covers what the tender package should say so that every bid describes the same building.

The fix is rarely more pages. It is a short list of decisions made by the tender author instead of left to each estimator. Most of them take a few lines to write and save days of levelling later.

The wall schedule and the finish schedule

Start with a partition schedule that has a tag for every wall type. Each tag should give stud depth, gauge and spacing, board layers and type, insulation, and whether the wall is rated or acoustic. Where a rating applies, name the listed assembly the designer intends. Do not leave the bidder to find one.

Then state the finish level by room or zone. Levels 0 to 5 are defined in GA-214 and ASTM C840, and both are free to cite. A note that says only "paint ready" leaves a Level 4 and a Level 5 bidder twenty percent apart on the same corridor. If lighting is critical, say where. Long corridors with side lighting and feature walls with a gloss paint are the usual Level 5 candidates.

Keep the two schedules cross-referenced. If a room appears on the finish schedule, every wall in it should appear on the partition schedule, and the other way round. Bidders notice mismatches, and each one resolves a mismatch in the way that suits the price.

Details that move the price

Some items look small on a drawing and are large on a bid. Put each one in writing, in the tender and not only on a detail sheet bidders may never open.

  • Head of wall deflection. Say which partition types need a deflection track or clip and the deflection the structure is expected to move. A tall floor plate with deflection on every wall is a different price than one with deflection on a few.
  • Backing and blocking. State whether in-wall backing for millwork, grab bars and equipment is shown, who supplies it and who locates it.
  • Ceilings. Name grid and tile, drywall ceilings and bulkheads separately, with heights. Bulkheads are the item most often assumed to belong to someone else.
  • Penetrations and firestopping. Say whose scope the firestop at rated walls is. See whose scope firestopping is for the usual gap.
  • Insulation. Say whether it is acoustic or thermal and who supplies it.
  • Hoisting and access. Note the elevator, loading dock and any lift available, and the hours they can be used.

Where a detail is still open at tender, say so and ask for an allowance with the quantity stated. An allowance with no quantity is only a placeholder, and bidders will not all use the same one.

Phasing, heat and site conditions

A drywall crew can only work as fast as the site lets it. Tell bidders how many floors or zones are open at once, how many mobilizations the schedule expects, and the working hours. In an occupied building, say so, along with any noise or dust limits. Those limits change the crew size and the sequence.

State who provides temporary heat and from what date. Taping compound needs a stable temperature, and the manufacturer's instructions govern how cold a space can be. If heat is not in the drywall scope, the tender should say that plainly.

Tender items and the question each one answers
Item in the packageQuestion it settlesIf it is missing
Partition schedule with tagsWhat is being built, wall by wallBidders price by area
Finish level by roomHow much finishing labour is carriedLevel 4 and Level 5 bids mixed together
Deflection noteWhich walls need a deflection headAllowances differ widely
Backing responsibilityWho supplies and locates blockingA change order after boarding
Phasing and mobilizationsHow many return visits are pricedPatching treated as extra
Heat and hoistingWho provides them and whenExcluded by every bidder

Ask bidders to answer in one format

A tender that closes the gaps still gets uneven replies if each bidder writes their own. Attach a short bid form with the same lines for everyone: drawings and addenda acknowledged, partition tags priced, finish level assumed, inclusions and exclusions, crew size and duration.

Ask for unit prices on the items likely to change, such as an added wall type, a finish level upgrade or an extra patching visit. They give you a basis for pricing changes after award, agreed while you still have competing bids.

Allow a question window and issue every answer as an addendum to all bidders. A reply that goes to one bidder is a scope difference you created.

We self perform steel stud framing, boarding, taping and finishing, so a complete package lets us price the whole drywall scope in one pass. Send drawings, and where the package has gaps we will list the assumptions we carried.

FAQ

Tender packages, answered.

What general contractors ask us while they assemble a drywall package for tender.

Enough that two estimators reading it reach the same scope. That means a tagged partition schedule, finish levels by area, head of wall details, ceiling and bulkhead scope, and the phasing and site constraints. More paper is not the goal. Each missing item is one bidders will price differently.
Yes, or at least by zone. Where the spec is silent, name the level bidders should carry. Corridors with strong side lighting and walls with gloss paint are worth calling out separately, because they are where a higher finish level is most often needed.
Name one party in the tender. Backing is placed before boarding, and someone has to locate it from the millwork and equipment drawings. If the drywall scope carries it, say so and give the drawings it is located from. If another trade does, state that.
An answer given to one bidder changes the scope for that bidder only. Issuing every answer to all of them keeps the bids on the same basis and leaves a written record if the scope is questioned after award.