Etobicoke, Toronto

Commercial and industrial drywall contractor in Etobicoke

Office, industrial and retail drywall across Etobicoke, from the 427 employment lands to the Islington and Six Points office nodes.

What we build in Etobicoke

Etobicoke is unusually mixed. The employment lands along Highway 427 and the airport corridor are industrial and logistics. The Six Points and Islington nodes are office and increasingly residential. The Queensway and Lake Shore carry retail, restaurants and older commercial stock being converted. Each of those produces a different kind of drywall package.

  • Office and warehouse build-outs in the 427 and airport employment lands
  • Tenant fit-outs in Islington and Six Points office buildings
  • Retail and restaurant build-outs along The Queensway and Lake Shore
  • Condominium amenity and corridor work
  • Fire-rated assemblies, shaft walls and rated demising walls
  • T-bar and acoustic ceilings, drywall bulkheads and ceilings

Older building stock, and what it hides

A good share of Etobicoke's commercial buildings are decades old, and renovation work in them turns up conditions a new build never has. This is the main reason we walk a renovation site before bidding it rather than pricing from drawings alone.

What we look for on an Etobicoke renovation walk
What we checkWhy it matters to the price
Existing wall constructionBlock, plaster and lath, or drywall each demolish differently
Whether existing walls are plumbOut of plumb structure adds furring that was never drawn
Slab and deck conditionTrack fastening and floor levelling both change with the substrate
Existing rated assembliesA rated wall being cut has to be restored to a listed detail
Designated substances surveyOlder buildings need this settled before demolition starts
Access and hoistingA tight urban site can add more cost than the drywall itself

Industrial work near the 427 and the airport

The employment lands work looks much like our Brampton and Mississauga projects. Office pods inside a shell, washroom and lunchroom blocks, demising walls between units, and rated separations. Clear heights mean lift access, and unconditioned space in winter means temporary heat is a schedule item rather than an afterthought.

Where a building sits inside the airport operating area, site access and security clearance add lead time. We would rather build that into the schedule at tender than explain it in week one.

Retail and restaurant build-outs

Retail and restaurant work along The Queensway, Lake Shore and the plaza units through central Etobicoke runs on a different clock from office work. The tenant is paying rent from the day they take possession, so the schedule is driven by an opening date that was set before anyone priced the drywall.

  1. Confirm the landlord's construction rules early, because plaza and mall landlords set working hours, hoarding standards and delivery routes that are not on the drawings
  2. Check whether the unit is being handed over as a shell or with existing walls to demolish, since that changes the schedule more than the new work does
  3. Identify the rated demising walls between units, which in an older plaza are often not what the drawings assume
  4. Confirm ceiling heights against the mechanical layout before framing bulkheads, because restaurant exhaust routing regularly moves them
  5. Agree the sequence with the millwork and equipment suppliers, whose deliveries usually need the walls closed and painted first

Restaurant work adds two more items worth pricing openly. Moisture resistant board is normally required behind kitchen and washroom finishes, and the kitchen envelope often needs a rated separation that the tenant's designer has drawn but nobody has taken off. We call both out in the bid rather than treating them as assumed inclusions.

Working with us

We bid as a subcontractor from your drawing set and self perform framing, boarding, taping and finishing, so the scope handoffs inside the drywall package stay ours to manage.

  • Two million dollar commercial general liability, certificate on request
  • WSIB coverage in good standing
  • Non-union open shop
  • Five years and more of commercial and industrial work across the GTA

For the underlying scope, see commercial drywall and fire-rated assemblies.

FAQ

Etobicoke drywall questions

What general contractors and property managers ask before awarding the work.

On a renovation, yes, and we would rather insist on it. Older Etobicoke commercial buildings hide conditions that drawings do not show, including out of plumb structure, plaster and lath behind newer finishes, and rated assemblies that have been cut into over the years. A walk turns assumptions into a firm number.
Yes. Site access and security clearance add lead time and sometimes restrict working hours, so we build that into the schedule at tender rather than discovering it after award. Tell us the access requirements with the drawings and the dates we quote will account for them.
Yes, and it has to be restored to a listed assembly rather than simply patched. That means matching the board type and layers, closing the penetration with a tested firestop detail, and documenting what was installed. A rated wall that has been cut and skimmed over is a deficiency waiting to be found at inspection.